SUPPORTING DOCUMENT: Innovation Award (24 MW project in 96 hours in Oman)


Powering our Way to History:
How a 24 MW power plant was installed in Oman in just 96 hours 


See how Altaaqa Global was able to install a 24 MW power plant in 96 hours...

Altaaqa Global installed a 24 MW power plant in 96 hours in Oman, which were able to stabilize the power grid in the country. The most advanced equipment were deployed for the project that is known as the fastest power plant installation in the history of the energy industry. 

To avoid the catastrophic economic and social effects of load shedding and of power outages, the Government of Oman and the Oman Power and Water Procurement Company (OPWC) sought for an immediate solution that would be able to support the increased energy demand during the summer months. The Government wanted a 24 MW interim power plant to be built in just a matter of days in an area where there are no substations.

The installation of the 24 MW power plant was primarily aimed at avoiding grid instability and widespread power failure, and the disastrous effects they might have on industries, businesses and society. At that time, when temperatures are peaking at 50°C and when the deadline was so tight, no rental power company thought that the project was doable. Altaaqa Global CAT Rental Power (ATG), however, braved the situation and presented a plan that convinced the Government to award the contract to it. 

Description and Development

For the 24 MW project, Altaaqa Global installed the most advanced Caterpillar equipment, never before seen in any power plant in the world.


The equipment came with a fully automated control system, connecting a 24 MW power plant directly to the grid, without the need for a substation.


As the power equipment deployed for the project had less equipment and less accessories, transportation costs were kept at a minimum, the time needed to install the power plants was dramatically reduced and the manpower needed to complete the project was lessened.





       Equipment were “lego-like” that they can be plugged and played for easier and swifter installation and commissioning.




Working in such a harsh condition and in the face of technical and infrastructural deficiency in Oman, thanks to a flawless project delivery execution, ATG installed the 24 MW power plant in Oman in just 96 hours – touted to be the fastest installation in the history of the energy industry.

Impacts and Benefits

With the successful installation of the 24 MW power plant in just 96 hours, the stability of electricity grids was maintained and the peak performance of the country’s power infrastructure was ensured. Ultimately, power outages were averted and ruinous economic and financial repercussion of power outages were instantly averted.

The temporary power plants installed by ATG was able to immediately avoid economic turmoil in an area which was on the brink of suffering from load shedding or power outages. In addition, the project was also able to protect the cash flow of the Government, sparing it from needing to build a permanent infrastructure, when the spike in power demand would only last for two to three months. 



Reasons

The power plants installed by ATG and the approach it employed in completing the 24 MW Oman project in just 96 hours represented a breakthrough in the industry. What was previously regarded as undoable were made possible, thanks to cutting-edge innovation, and ground-breaking service delivery methods. In addition, ATG was able to hurdle the technical and infrastructural challenges without putting a financial burden on its client. In fact, despite the novelty of ATG’s technologies, they were proven to be more cost- and process-efficient, saving the client costs in infrastructure, transportation, manpower, installation and commissioning.

The record-breaking feat would not have been possible if not for ATG’s technological and methodological innovation. As a quote from John Maynard Keynes says, “Ideas (innovation) shape the course of history” – and ATG had proven this true. 

See how Altaaqa Global was able to install a 24 MW power plant in 96 hours...